Company

Abo Rugia Mining

Category

Gold residue processing

Technology

Carbon-in-leach (CIL)

Design capacity

1,500 tons per day

Production milestone

First experimental production commenced on 19 September 2014

Explore Abo Rugia Mining

CIL Gold Processing Plant

The carbon-in-leach plant processes traditional gold-mining residue with a design capacity of 1,500 tons per day and gold recovery above 95 percent.

Project Overview

Abo Rugia Mining entered traditional mining residue treatment in 2012 and became an early Sudanese participant in the field, qualifying for work around Wad Bushara, Shawir, and Al-Khayari.

  • CIL processing technology
  • Gold recovery exceeding 95 percent
  • First experimental production on 19 September 2014

Supporting Infrastructure

Substantial site infrastructure supports the processing plant and its workforce.

  • 4 MW electrical generation facility
  • Approximately 70 km water-transfer system
  • Laboratory, stores, workshop, clinic, fuel station, accommodation, dining, and mosque

Environmental Relevance

Modern residue treatment and scientific transport practices help reduce negative environmental effects associated with traditional mining.

Project Media

Project Media

Plant conveyor line

Processing mill

Material feed system

Crushing and conveying

Process drive equipment

Material discharge

Furnace work preparation

Crushing plant

Smelting operation

Processing complex